Ñý¼§Ö±²¥

5/25- Williams Hall/ISB Construction Updates

Work in progress:

  • Temporary steam condensate line in tunnel is complete along with taps on main condensate and steam feeds for future connections.
  • Chilled water line hangers are being installed above AHUs in Williams mechanical room.
  • Steel erection in sequence 4 & 5.
  • Steel detailing in sequence 2 & 3.
  • Metal floor decking has begun in sequence 1.
  • Form basement retaining wall between column line B & C.
  • Removal of windows from Williams Hall west side - window protection has been installed.
  • Abatement and demolition of instructional labs on the first floor south end has begun.

Looking forward:

  • Continue with steam and condensate line work in the tunnel.
  • Continue with the chilled water line extensions above the AHUs in the basement.
  • Continue steel erection in sequence 5 & 6.
  • Continue steel detailing in sequence 2 & 3.
  • Start metal decking in sequence 2.
  • Form elevator #2 pour #3.
  • Pour lift #3 at stair #3.
  • Start roof replacement on Williams Hall west side.
  • Continue with demolition of brick on west side of Williams Hall.
  • Continue with demolition and abatement on the 1st floor (south) of Williams Hall.
POSTED: Wednesday, May 25, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM