Ñý¼§Ö±²¥

10/03- Williams Hall/ISB Construction Updates

ISB

Work in Progress

  • Brick work along line 17, from B to G is in progress.
  • Continue retaining wall along line 8.
  • Continue curtain wall installation at the northeast side.
  • Finalize pre cast and brick work along A line.
  • Continue the pouring of the hydraulic slab on the east side, lines 14 to 17.
  • CMU installation in penthouse completed.
  • Start backfilling for slab on grade east side of the building, lines 14 to 11.
  • Start Hydraulic slab on the east side of the building, lines 8 to 11.
  • Start CMU wall in basement, lines 1 to 7.

Looking Forward

  • Continue pre cast and brick work along line 17, from B to G.
  • Pour Hydraulic slab on the east side of the building, lines 14 to 17.
  • Finalize installation of the CMU in penthouse.
  • Continue CMU wall in basement, lines 1 to 7.
  • Continue hydraulic slab on the east side of the building, lines 8 to 11.
  • Continue backfilling for slab on grade, east side of the building, lines 14 to 17.

Williams Hall

Work in Progress

  • Continue piping work for steam station in mechanical room.
  • Ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17 is in progress.
  • Continue plumbing work for W3: roof drains, storm lines, etc..
  • Continue electric rough installation in basement, and 2nd floor lines 1 to 17.
  • Continue duct work installation in 1st floor east side of the building.
  • Continue final painting concrete.
  • Finalize drywall for W3.
  • Finalize installation of steel for exhaust fans on roof for W3.
  • Start painting walls for W3.

Looking Forward

  • Continue piping work for steam station in mechanical room.
  • Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
  • Continue plumbing work for W3.
  • Continue electric rough installation in basement.
  • Continue final painting concrete.
  • Continue installation of mill work for W3.
  • Continue fireproofing in penthouse and 2nd floor on the east side of the building.
POSTED: Monday, October 3, 2016 09:43 AM
Updated: Saturday, December 3, 2022 01:02 AM