10/06- Cunningham Hall Renovation Updates

Work in Progress

  • Complete drywall work in basement, Human Anatomy Lab.
  • Taping in Human Anatomy Lab is in progress.
  • Continue north side corridor curtain wall installation.
  • Continue cleaning operations.

Looking Forward

  • Continue detailing work in basement, Human Anatomy Lab.
  • Continue north side corridor curtain wall installation.
  • Start installation of the interface of the north side curtain wall and the green house glass.