Ñý¼§Ö±²¥

3/17- Cunningham Hall Renovation Updates

Work in Progress:

  • Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15.
  • Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
  • Steam reducing station in the 3rd floor east mechanical room is approximately 10% complete.
  • Completed the installation of the temporary roof duct work.
  • Electrical demolition work in the tunnels is complete.
  • Containment is in place for the abatement of AHU #2 in the 3rd floor west mechanical room.

Looking ahead:

  • AHU#2 will be shut down 7:00am-3:00pm for abatement Monday through Thursday (3/21-3/24).
  • Roth will be piping the control valves and coils to AHU#1 in the 3rd floor east mechanical room.
  • Abatement to start in the 3rd floor ceilings.  Tuner will coordinate with Mark Moser.
  • Ceiling grid to be removed on the second floor south west corridor.
  • Complete foundations and start retaining wall pours scheduled for 3/22.
  • Start foundations and hoistway walls for new elevator.
POSTED: Thursday, March 17, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM